CRRC Updates regarding the SEPTA Multilevel cars order

Per an recently published article concerning CRRC

Updates on the CRRC order of Multilevels are as follows:

– Pilot cars are in final assembly and inspection at the plant in China

-Pilots expected to be delivered within the next few months (Middle of 2022)

-Purchase order cost increased slightly from $137.5 million to $138 million

-Once pilot cars tested and approved, cars would be assembled for an year and a half